Crated Industrial Equipment from Belgorod to Akkuyu: Shipment by 120 m³ Truck and Trailer

October 21, 2026

Industrial equipment for the Akkuyu Nuclear Power Plant, packed in wooden crates in Belgorod, was loaded onto a 120 m³ truck-and-trailer combination; the shipment set off on 13 November 2025 and was unloaded on 24 November.

Client
Akkuyu Nuclear JSC
Cargo
Industrial equipment in wooden crates
Vehicle
120 m³ truck-and-trailer combination (tilt)
Route
Belgorod (Russia) → Tuapse–Taşucu Ro-Ro → Akkuyu area
Dates
Loaded 13 November 2025 · unloaded 24 November 2025

Challenge

The industrial equipment prepared in Belgorod for the Akkuyu power plant project was packed in wooden crates. With crated loads of this kind, choosing the right vehicle volume and securing the crates so they cannot shift along the way are prerequisites for damage-free delivery.

Solution

  • Vehicle selection: A 120 m³ truck-and-trailer combination matching the volume of the load was planned.
  • Pre-loading checks: The dimensions and weights of the crates were checked before loading, and the fit between vehicle and load was verified on site.
  • Load securing: The crates were secured at multiple points with ratchet straps.
  • Route and customs: The shipment was carried to Türkiye on the Tuapse–Taşucu Ro-Ro line, customs procedures were completed at Taşucu and the cargo was delivered to the power plant area.

Result

Loaded in Belgorod on 13 November 2025, the equipment was unloaded on 24 November 2025. 12 photos of the operation are in the gallery below.

This shipment is part of the Akkuyu supply line we run for Akkuyu Nuclear JSC.