Project logistics is the end-to-end planning, engineering and execution of transport for large-scale industrial and infrastructure projects, where every component — from a 330-tonne reactor vessel to thousands of tonnes of structural steel — must reach the construction site in a contractually defined sequence. Voltim Global, with offices in Istanbul, Mersin and Moscow, coordinates this entire chain from a single point, from feasibility studies through to final site delivery.
How does project logistics differ from standard freight forwarding?
Standard freight forwarding moves repeatable, containerised shipments along established schedules. Project logistics, by contrast, is engineered around a construction programme: each movement is a one-off operation involving out-of-gauge dimensions, extreme weights and a fixed erection sequence, where a late arrival can idle cranes, crews and contractual milestones. The discipline therefore starts long before transport — with load analysis, route surveys and critical point identification covering bridges, tunnels, overhead lines and turning radii. Under the Turkish Highway Traffic Regulation, a road movement exceeding the general limits — 2.55 metres in width, 4 metres in height or 40 tonnes gross combination weight — requires a Special Load Transport Permit, so permit engineering is part of the plan from day one. Voltim Global performs this engineering feasibility — load analysis, route study and critical point identification — and carries out oversized and heavy cargo moves with its partner network as an integrated part of the wider project plan.
How is logistics planned under FIDIC and EPC contracts?
In EPC and turnkey projects — typically contracted under the FIDIC Silver Book, which places design and execution responsibility on the contractor — logistics failures translate directly into delay damages. Logistics planning therefore has to mirror the contract itself: delivery obligations, milestone payments and site handover dates are converted into a transport schedule with defined responsibilities at every interface. Voltim Global joins projects at the feasibility stage, well before mobilisation, so route studies and permit lead times can be priced into the tender. During execution, weekly progress reports, KPI and milestone tracking give the EPC contractor documentation aligned with its own employer reporting, while project cargo and erection All Risks insurance closes the risk allocation between marine transit, inland transport and on-site handling.
Why does critical path analysis matter in project cargo logistics?
Critical path analysis identifies which cargo movements directly determine the project completion date. A steam turbine, transformer or reactor component is usually a long-lead item: if it arrives late, erection stops, and every downstream activity slips with it. Logistics planners therefore classify each consignment by float — how much delay it can absorb before touching the critical path — and build buffers around the items with none. Permit approvals, vessel fixtures, seasonal road restrictions and port congestion are all mapped as schedule risks. Voltim's critical point identification and route studies feed this analysis: a longer routing that avoids a weight-restricted bridge may protect weeks of programme time. The output is a transport plan sequenced against the construction schedule rather than against transport convenience.
How is multimodal transport coordinated on a large project?
Large project components rarely move door-to-door by a single mode. A typical chain combines a heavy-lift or breakbulk vessel for the ocean leg, river barges or rail for inland corridors, and hydraulic modular trailers for the final kilometres — with engineered transhipments at each interface. The risk in multimodal operations concentrates at those interfaces: lifting plans, lashing calculations, quay strength and crane capacity must all be verified before the cargo ever ships. Voltim Global coordinates sea, road, river and rail combinations from a single point, plans port and rail transhipments, and integrates transit customs declarations so cargo is not held at borders between modes. Cargo classes and handling methods are described in detail on our project cargo page.
How are site delivery windows managed?
Construction sites take deliveries in windows, not at will. Laydown areas are limited, heavy-lift cranes are booked by the day, and erection crews work to a fixed sequence — so a component arriving early can be as disruptive as one arriving late. Delivery windows are agreed with the site erection team and locked into the transport schedule; oversize road convoys in Türkiye typically move at night under escort, within the route and time conditions written into each Special Load Transport Permit. For Türkiye's first nuclear power plant at Akkuyu, Voltim has delivered more than 450 supply shipments to the site region since March 2024, with permit management and daily reporting, so the customer always knew which shipment would arrive, and when. That daily cadence — rather than weekly summaries — is what site delivery management demands.
How are nuclear and energy project components transported?
Energy projects generate the heaviest single pieces in logistics. According to World Nuclear News, the VVER-1200 reactor pressure vessel installed at Akkuyu — a plant of four units totalling 4,800 MWe, per the World Nuclear Association — weighs some 330 tonnes at 4.5 metres in diameter and 12 metres in height. Pieces of this class travel by heavy-lift vessel to a project berth and then by self-propelled modular transporters over engineered routes, with civil works wherever the ground or existing structures cannot carry the load. The same methodology scales across thermal, hydro, wind and solar projects, refinery and gas processing plant modules, mining conveyor systems, and bridge, tunnel, metro or airport segments. Voltim's nuclear scope is presented on the nuclear project transportation page.
Key facts: project cargo logistics
- Under the Turkish Highway Traffic Regulation (Article 128), road vehicles are limited to 2.55 m width, 4.00 m height and 40 tonnes gross combination weight for five-or-more-axle combinations (44 t only for certain intermodal container combinations); loads beyond these limits require a Special Load Transport Permit for each movement.
- According to the World Nuclear Association, the Akkuyu plant comprises four VVER-1200 units totalling 4,800 MWe and is expected to meet about 10% of Türkiye's electricity needs.
- World Nuclear News reports that the VVER-1200 reactor pressure vessel installed at Akkuyu unit 1 weighs 330 tonnes, measuring 4.5 m in diameter and 12 m in height.
- According to the IAEA, construction of Akkuyu unit 1 — Türkiye's first nuclear power plant — began in April 2018.
- The FIDIC Silver Book is the international standard contract form for EPC/turnkey projects, placing design, execution and schedule responsibility on the contractor — the framework within which project logistics plans are drafted.
If you are preparing an EPC tender or need a logistics plan for an energy, industrial or infrastructure project, contact Voltim Global for an engineering feasibility study and a detailed project quote.
Frequently Asked Questions
What is project logistics and which projects does it cover?
How is the project logistics process managed?
Which transport modes are used for project cargo?
Which documents and permits are required in project logistics?
How is project logistics pricing determined?
From the guide: questions about this service
Other Services
Voltim's complete end-to-end logistics solutions
Air Freight
Airport-to-airport or door-to-door air freight with partner airlines and air cargo agents: general and urgent cargo, dangerous goods (DGR) and project spare parts, with customs and road connections handled from a single point of contact.
View
Sea Freight
FCL and LCL sea freight at competitive rates on major port routes through our global agent network.
View
Road Transport
TIR and groupage road logistics across Turkey, Europe and Central Asia — contracted carriers, daily tracking and ADR shipments with certified partners.
View
Customs Brokerage
Import, export and transit declarations handled by our contracted licensed customs brokers at Turkish customs gates.
View
Warehousing & Distribution
Warehousing through our partner warehouses — climate-controlled options, cross-docking, pick-pack and end-to-end distribution.
View
Logistics Insurance
All Risks marine, CMR, warehouse, project cargo and valuable cargo insurance, arranged through partner insurance companies.
View
Project Cargo
End-to-end management of heavy, oversized and special equipment cargo — feasibility, permits, transport and assembly coordination.
View
Cold Chain Logistics
End-to-end cold chain logistics for food, pharmaceuticals and sensitive products, carried out with partners holding the relevant certificates.
View
Hazardous Materials (ADR)
Dangerous goods transport (ADR Class 1-9) planned by Voltim and carried out with partners holding the required ADR certificates.
View
Real-Time Tracking
Follow your cargo via driver location from our mobile app, your customer panel and daily status reports — reachable 24/7.
View
Import Customs Clearance
Import declarations, HS code classification, customs lane tracking and inspection management at Turkish customs gates via our contracted customs brokers.
View
Export Customs Clearance
Export declarations, ATR, EUR.1 origin certificates and VAT refund — full export operations support.
View
Transit Customs
TIR carnet, NCTS T1/T2 transit declarations and ATA carnet — Europe-Turkey-CIS transit operations.
View
Bonded Warehouse Operations
Storage in partner bonded warehouses (types A, B, C, E) and free-zone facilities, with handling and inward-processing operations.
View
Trade Regulatory Consulting
HS code, product requirements, trade agreements and control lists — sector-specific trade consulting.
View
Tax & Exemptions
Inward processing, VAT refund and tariff exemption management — tax optimisation and correction processes.
View
Digital Customs and BILGE NCTS Login
BILGE and NCTS digital customs explained, with declarations handled via our contracted customs brokers.
View
Marine Cargo (All Risks) Insurance
All Risks (ICC A) marine cargo insurance — damage, loss, theft and natural disaster coverage in sea and road transport.
View
CMR Insurance
CMR carrier-liability insurance for international road transport — 8.33 SDR/kg limit, with delay and special clauses.
View
Warehouse Insurance
Comprehensive coverage for stocks in bonded and standard warehouses — fire, flood, earthquake, theft and electrical fault.
View
Project Cargo Insurance
DSU, ALOP, EAR-clause project cargo insurance for industrial projects, power plants and wind turbines — risk-engineered.
View
International Transport Insurance
Single-policy All Risks cover for multimodal sea-and-road shipments, arranged through partner insurers — open cover annual policies and door-to-door protection.
View
Valuable Cargo Insurance
All Risks insurance with expert valuation for art, antiques, precious metals and high-value electronics, arranged through partner insurers.
View
Insurance Policy Management
Insurance cover arranged through partner insurance companies and agencies, with policy follow-up and claims support from a single point of contact.
View
International Road Freight
Full and partial truckload services between Turkey, Europe, Russia and CIS countries.
View
Full Truckload (FTL)
Direct, scheduled delivery of single-customer loads to the consignee location.
View
Less Than Truckload (LTL)
Economical, controlled groupage services for small-volume shipments, planned according to demand.
View
Oversized & Heavy Cargo
Special permits, route planning and escort organisation across the entire process.
View
Nuclear Project Transportation
Site access, vehicle tracking and delivery management for high-precision projects.
View
Container Transportation
Container operations between ports, warehouses, factories and project sites.
View
Bonded & Transit Transport
Support for T1 organisation, guarantee and document coordination processes.
View
Port and Site Delivery
Secure delivery from ports to warehouses, bonded warehouses, factories or project sites.
View
Crane & Forklift Operations
Equipment-supported organisation for loading, unloading and on-site operations.
View
Daily Vehicle Tracking & Reporting
Vehicle position tracking and regular client communication throughout the shipment.
View
Forklift Rental
12-tonne diesel forklift rental: loading, unloading and handling at construction sites, ports, factories and open storage yards; with or without operator.
View
Door-to-Door Delivery
End-to-end management from pickup point to final delivery address.
View
Freight from Russia to Türkiye and the Akkuyu NPP Supply Corridor
Supply logistics from Russia to Akkuyu NPP: Tuapse–Taşucu RoRo, road via Upper Lars or Iran, customs clearance in Taşucu and delivery to site.
View
Turkey–Iran Road Freight: FTL and LTL Trucking to and from Iran
Road freight between Turkey and Iran in both directions: FTL, LTL, oversized and ADR cargo via Gürbulak–Bazargan, with TIR, customs and daily tracking.
View
Europe to Iran Trucking via Turkey: the Kapıkule–Gürbulak Route
Truck transport from the EU to Iran through Turkey: Kapıkule entry, Gürbulak–Bazargan exit, TIR or T1 transit and EU loading run by our Budapest office.
View
Russia to Iran Road Freight via Georgia and Turkey
Road freight from Russia to Iran via Verkhniy Lars, Georgia, Sarp and Gürbulak–Bazargan under a TIR carnet, with loading coordinated by our Moscow office.
View
Russia–Iran–Turkey Transit Freight: Russia to Mersin by Road
Bonded road transit from Russia through Iran to Mersin, Turkey: 24 trips dispatched from 15+ Russian cities between 19 August and 30 September 2026.
View