Conventional freight transport moves standard-sized cargo from one point to another with a regular, repeated service. Project logistics, by contrast, manages heavy or out-of-gauge cargo, mostly one-off and tied to an investment's installation schedule, in a single plan that combines engineering calculations, permits, multimodal transport and delivery on site.
Where do the two models diverge?
The 24 tonnes of palletised cargo that a textile exporter ships every week is carried with a known vehicle, on a known route and in a known time. A 180-tonne power transformer bound for a substation, on the other hand, is carried once: its route is surveyed, the bridges are calculated, permits are obtained and it is set down on its foundation on site. In the first case, the measure of success is transit time and unit cost. In the second, it is keeping the investment's installation schedule on track.
| Criterion | Conventional freight | Project logistics |
|---|---|---|
| Cargo | Standard size, palletised or cartoned | Heavy, out-of-gauge, indivisible or high-value |
| Repetition | Regular, scheduled | Mostly one-off |
| Planning time | Days | Weeks, months on large projects |
| Engineering | Not needed or simple | Axle, lashing, lifting and route calculations |
| Permits | Standard transport documents | Special cargo permit in each country, port and site approvals |
| Price | Tariff or spot market rate | Project budget based on survey and scope of work |
| Delivery point | Warehouse or factory gate | Often the foundation or installation point |
| Insurance | Goods insurance and carrier's liability insurance | Project cargo policy, with optional delay cover |
Why is engineering part of the job?
For project cargo, the vehicle is not chosen by the cargo's dimensions alone; the weight distribution, lifting points and the road's load-bearing capacity are calculated together. These calculations turn into a transport plan and a method statement. The work starts before shipment with a project cargo feasibility study: route, port, vehicle and permit options are compared. In conventional freight, the step corresponding to this study is often just a vehicle booking.
What does being tied to a schedule mean?
On projects, every piece of equipment has a date by which it must be on site. Cargo that arrives earlier than this date creates costs for on-site storage, preservation and double handling. Cargo that arrives late, on the other hand, leaves the hired crane, the installation crew and subsequent work packages waiting. The vessel loading window, permit validity dates and crane booking are linked in a single timeline. A delay in one link shifts the others too.
Who is at the table?
- Investor and EPC contractor: set the schedule and delivery terms.
- Manufacturer: provides dimensions, weight, lifting points and packaging information.
- Project logistics company: builds the plan and coordinates carriers and permits.
- Port, vessel operator, crane company and customs broker.
- Highway authorities and, where necessary, the police or gendarmerie.
- Insurer and independent surveyor.
In conventional freight, this chain often consists only of shipper, carrier and consignee. In project logistics, as the number of stakeholders grows, the need for a communication plan and a single responsible coordinator becomes clear. The final step on site is explained in the setting equipment in place entry.
Which should be chosen when?
If the cargo is within legal dimensions and the delivery date is flexible, conventional freight is sufficient. If the cargo is out of gauge, if more than one mode of transport is needed, or if the cost of delay exceeds the transport charge, a project approach is required. There are also mixed cases: hundreds of standard cartons for a power plant project arrive by conventional freight, while the main equipment arrives by project transport. Insurance is also handled separately for project cargo; a project cargo policy is often issued instead of a goods policy.