Why is QA/QC documentation mandatory in nuclear projects?

Last updated:

Short Answer — QA/QC Documentation

QA/QC documentation is mandatory in nuclear projects because the fact that a piece of equipment was manufactured, transported and preserved in line with safety requirements can only be proven through records. Law No 7381 and the NDK's Management System Regulation require a quality plan, records and nonconformance management from the licensee and its suppliers. Material with incomplete records is not accepted on site.

Are QA and QC the same thing?

No. Quality assurance (QA) is the set of planned and systematic actions that provide confidence that the work will be done right from the start: procedures, quality plans, supplier audits, training and record-keeping. Quality control (QC) measures the product itself: dimensional checks, non-destructive testing, pressure tests, visual inspection. QA manages the process, QC verifies the result. In a nuclear project both must leave a written trail.

CriterionQuality assurance (QA)Quality control (QC)
FocusProcess and systemProduct and part
TimingBefore and throughout the workAt defined inspection and test points
Typical outputQuality plan, procedure, audit reportTest report, dimensional report, inspection record
AimPrevent errorsCatch errors

Where does the obligation come from?

Article 5 of Nuclear Regulatory Law No 7381 (Nükleer Düzenleme Kanunu) requires the authorised organisation to conduct its activities with an appropriate management system and to keep defined records. Article 7 of the same Law empowers the Nuclear Regulatory Authority (Nükleer Düzenleme Kurumu, NDK) to inspect contractors, subcontractors, suppliers and sub-suppliers as well. The details are in the Regulation on Management Systems in Nuclear Facilities, Radiation Facilities and Radioactive Waste Facilities, published on 27 April 2022 and last amended on 2 October 2026:

  • Quality plan: Sets out who will do the work, which standard will be followed, which records will be produced and how the product will be accepted (Art. 17).
  • Supply chain rules: Define the records the supplier will keep, methods for resolving nonconformances, measures against counterfeit or suspect items and acceptance criteria (Art. 15).
  • Nonconformance management: Deviations are recorded, their cause is analysed and corrective action is tracked.

What does a shipment file contain?

  1. Manufacturing records: material certificates, welding and non-destructive testing reports, the equipment passport.
  2. Factory acceptance test records and the signatures of hold points and witness points attended by the customer.
  3. Preservation and packing records: preservation method, amount of desiccant, crate and label details.
  4. Transport records: loading photos, lashing plan, seal numbers, shock and tilt sensor data, temperature and humidity logs, CMR or bill of lading.
  5. Delivery documents: packing list, list of KKS-coded labels and the documents accompanying the shipment.

How does a nonconformance report (NCR) work?

An NCR is opened when a requirement is not met, for example when a crate arrives damaged, a sensor shows a threshold exceedance or the heat number on the certificate does not match the one on the part. The report records the deviation, its possible impact and the decision. There are four typical dispositions: use as is, repair, rework and reject. The decision is taken jointly by the party responsible for the design and the buyer's quality department. A part with an open NCR is not released for installation.

Who prepares it and who is responsible?

  • Manufacturer: Prepares the QC records and the product file.
  • Buyer or main contractor: Approves the quality plan, attends witness points and audits the supplier.
  • Independent inspection organisation: A third party authorised by the NDK monitors the critical stages.
  • Carrier: Is responsible for complete transport and handling records.

What does missing documentation cause on site?

During receiving inspection, documents and parts are matched one to one. A crate whose sensor record cannot be read or whose seal number does not match the record is moved to the quarantine area; the installation schedule waits until the gap is closed. For equipment of a high safety class, this wait can last weeks, because a missing record cannot be produced after the fact; either the test is repeated or the part is rejected.

How does Voltim Global support this?

In nuclear project transport, Voltim Global keeps loading photos, seal and delivery records linked to the shipment file. Each shipment is followed up daily until delivery and its status is reported to the customer.

Frequently Asked Questions

Is the QA/QC file sent together with the shipment?
In practice two sets are created. The main manufacturing file is usually uploaded electronically to the buyer's document system in advance; the shipment itself is accompanied by the packing list, label list, delivery note and sensor recording devices. The site acceptance team compares the physical part with the information in the pre-approved file. Every difference between the shipment and the file is recorded as a finding that stops acceptance.
How is damage that occurs during transport handled under QA/QC?
The damage is recorded with the carrier's report and photographs, after which the buyer opens a nonconformance report. The design owner decides whether the part is usable. The insurance process runs separately; receiving compensation does not mean that the NCR is technically closed. The part is released for installation only with the design owner's approval; if repair is needed, the repair procedure and subsequent tests are also added to the file.
Is an ISO 9001 certificate sufficient for nuclear supply?
Not on its own. ISO 9001 offers a general quality management framework applicable to every sector; in nuclear projects, a project-specific quality plan, buyer audits and, for some equipment groups, an NDK authorisation or compliance with nuclear quality standards such as NQA-1 may be required in addition. The buyer also puts the supplier through its own audit before contracting.