How is out-of-gauge cargo loaded and unloaded?

Last updated:

Short Answer — Loading and Unloading Out-of-Gauge Cargo

Depending on its weight and shape, out-of-gauge cargo is put onto the trailer by lifting it with a crane, driving it up a ramp on its own wheels or tracks, using a forklift, or with a jacking and skidding system. Before loading, the ground, centre of gravity and lifting points are checked; the cargo is placed in its position on the stowage plan and secured with calculated lashing.

How is the loading method chosen?

The choice is determined by the cargo's weight, whether it has lifting points, the space on site and the ground. The same 60-tonne piece of equipment might be loaded with an overhead crane at the factory, a mobile crane on a construction site, or by jacking and skidding in a tight off-port area.

MethodSuitable cargoPoint to watch
Mobile craneMost cargo with lifting pointsGround pressure from the crane outriggers, capacity at the boom angle
Crawler crane or tandem liftVery heavy or long piecesSet-up area and time, load sharing between the two cranes
Forklift, telehandlerShort, compact cargo with fork pocketsCentre of gravity staying within the fork length
Driving up a rampConstruction machinery, wheeled or tracked equipmentRamp angle, trailer deck height, slippery surfaces
Jacking and skiddingHeavy cargo such as transformers and presses on sites where a crane cannot be set upLoad capacity of the jacking points, flatness of the skid track
Driving under from trestlesCargo to be moved by hydraulic trailer or SPMTMatching trestle height with platform stroke

The difference between crane types is explained in the entry on mobile vs crawler cranes, and the jacking and skidding technique in jacking and skidding.

What is checked before loading?

  • Are the weight and centre of gravity marked on the cargo, and do they match the drawing?
  • Are the lifting lugs certified; are the capacities of slings, shackles and spreader beams sufficient?
  • Is the ground at the crane and vehicle positions adequate for the load; have load-spreading mats been laid if needed?
  • Are there power lines, building projections or traffic in the work area; has the area been cordoned off?
  • Is the wind speed below the crane's operating limit?
  • Can the trailer deck take the point load of this cargo; are timber or steel blocks ready?

For heavy and high-risk lifts, these checks are formalised in a written lifting plan.

How are stowage and lashing done?

  1. Position: The cargo's centre of gravity is placed on the trailer's design point; the axle load distribution has been calculated for this position.
  2. Support: The cargo is spread over the deck with blocks or beams so as not to create point loads; anti-slip mats are placed.
  3. Lashing: Chains or straps are fitted in the number and at the angle given in the lashing calculation.
  4. Measurement: Once loading is complete, height, width and length are measured again on the vehicle and compared with the values in the permit.
  5. Record: Photos and a checklist are kept; a surveyor's approval is obtained if required.

Details of the lashing calculation are given in the entry on lashing force under EN 12195-1; inspection by an independent surveyor is added to these steps when the insurer or consignee requires it.

What is different when unloading?

The unloading point is often harder than the loading point: the ground may not be ready and the space may be tight. Lashings are not fully removed until the crane has partly taken the load. If the cargo is to be set down on temporary trestles, their positions are marked in advance. The consignee carries out the first inspection after unloading and, if there is damage, draws up the report on the spot.

Who is responsible?

Responsibility is determined primarily by the contract. Article 17 of the CMR Convention can relieve the carrier of liability for damage arising from loading, stowage and unloading where these operations were performed by the sender or the consignee. In practice, the sender is responsible for the accuracy of the cargo data, the crane company for the lifting operation, and the carrier for the suitability of the vehicle and road safety. Details are in the entry on liability in out-of-gauge transport.

How does Voltim Global help with this?

Voltim Global organises crane- and forklift-supported operations together with the transport plan, working with its partners; it does not send the vehicle on its way without comparing the post-loading measurements with the permit values.

Frequently Asked Questions

How is cargo without lifting points lifted?
First, a lifting drawing is requested from the manufacturer; it defines where the slings may pass. Slings are used with edge protectors against sharp corners and with a spreader beam to keep the load balanced. For sensitive equipment where no lifting point can be defined, the cargo is carried on a lifting frame or skid placed underneath it. This frame is also calculated and documented separately.
Why are dimensions measured again after loading?
The dimensions on the drawing belong to the cargo itself; the dimensions on the vehicle add the deck height, blocks and lashing equipment. The permit is issued for this final measurement, and it is also what is checked at inspections. A difference of a few centimetres can mean a risk of striking an overpass or a fine for breaching the permit.