Short Answer — Nuclear Regulatory Authority (NDK)

The Nuclear Regulatory Authority (Nükleer Düzenleme Kurumu, NDK) is the independent authority that regulates nuclear energy and ionising radiation activities in Türkiye, issues licences and permits, carries out inspections and imposes sanctions. Construction licences for the Akkuyu NPP, permits for transporting radioactive material and the inspection of nuclear suppliers all fall within its remit. Its legal basis is the Nuclear Regulatory Law No. 7381.

When and how was the NDK established?

The NDK was established in July 2018 by Decree Law No. 702 and took over most of the regulatory duties previously carried out by the Turkish Atomic Energy Authority (TAEK). Today's legal framework consists of the Nuclear Regulatory Law No. 7381 (Nükleer Düzenleme Kanunu), adopted on 5 March 2022 and published in the Official Gazette (Resmî Gazete) of 8 March 2022, and Presidential Decree No. 95. The Authority is affiliated with the Ministry of Energy and Natural Resources (Enerji ve Tabii Kaynaklar Bakanlığı). Its decision-making body is the Nuclear Regulatory Board; its five members, including the Chair, are appointed by the President of the Republic.

What does it do?

The Law groups the NDK's activities under the heading of "regulatory control": regulation, assessment, authorisation, inspection and enforcement.

  • Regulation: It issues regulations and guides. Rules in areas such as management systems, safety, radiation protection and nuclear export and import control are set by NDK regulations.
  • Licence: Mandatory for operating a nuclear facility, a radiation facility or a radioactive waste facility.
  • Permit: Site preparation, the manufacture of certain equipment, construction, commissioning, and the import, export, transport and transit of radioactive materials are subject to permits (Law 7381, Art. 4).
  • Certificate of authorisation: Required for equipment manufacturers, third-party inspection companies and personnel designated by the Authority.
  • Inspection: Can be carried out unannounced and on any day, including public holidays; contractors, subcontractors and suppliers are also covered (Art. 7).
  • Enforcement: Administrative fines, and restriction, suspension or revocation of an authorisation.

The NDK's role at Akkuyu NPP

The construction licence for Akkuyu Unit 1 was issued in April 2018 by TAEK, shortly before the NDK was established. The licence for Unit 2 was issued in August 2019, for Unit 3 in November 2020 and for Unit 4 in October 2021. The commissioning and operation phases of each unit are also subject to separate authorisation. In April 2024 the NDK also granted site approval for the İnceburun site in Sinop.

How does it affect logistics?

Most of the equipment bound for the plant is not radioactive; no NDK transport permit is needed to carry a turbine rotor or a reactor pressure vessel (see is nuclear equipment radioactive?). The effect is indirect, but strong:

AreaImpact on logistics
Management system rulesThe carrier is asked for records, traceability and non-conformity reporting.
Supplier inspectionThe transport company must be open to inspection by the buyer and the NDK.
Safety and physical protectionTrustworthiness verification, vehicle searches and escorts apply at site entry (see physical protection).
Nuclear import controlGoods on the NDK's list require an import permit before customs.
Radioactive materialFresh fuel and radioactive sources are transported with an NDK permit and under ADR Class 7 rules.

The Regulation on Nuclear Export and Nuclear Import Control, published in October 2025, makes the export of items designed for nuclear use and of dual-use items, and the import of listed items, subject to a permit. An import permit cannot be transferred or used outside its scope. Goods arriving in a free zone are also subject to this rule.

What does the NDK not do?

The NDK does not issue road permits, does not handle customs procedures and does not issue K- or L-type authorisation certificates to transport companies. Out-of-gauge permits are the responsibility of the KGM (General Directorate of Highways), customs procedures of the Ministry of Trade (Ticaret Bakanlığı), and transport authorisation certificates of the Ministry of Transport and Infrastructure (Ulaştırma ve Altyapı Bakanlığı). The NDK asks a different question: is the activity safe, secure and properly recorded?

Frequently Asked Questions

What is the liability limit for the transport of nuclear material?
Under Article 13 of Law No. 7381, the operator's liability for nuclear damage arising from the transport of nuclear material is limited to 80 million euros; for transits through Türkiye the limit is 700 million euros. The operator must provide insurance or financial security for this amount. Since a 2024 amendment, the operator may, with the Authority's approval, transfer this obligation to the carrier by written contract; the carrier is then liable as if it were the operator.
Does NDK inspection also cover the transport company?
It can. The Law empowers the NDK to inspect the contractors, subcontractors, suppliers and sub-suppliers of an organisation it has authorised. A carrier working on a nuclear project is therefore expected to keep its records ready for inspection and to document the required competencies. Inspections may be scheduled or unscheduled, announced or unannounced, and carried out on any day, including public holidays; inspectors may request records and documents and take samples.
Should a company importing equipment for a nuclear project apply to the NDK?
Yes, if the item is on the List of Items Subject to Nuclear Import Control published by the NDK; no procedure can be carried out without an import permit. Conventional equipment that is not on the list is subject to the general import regime. If classification is unclear, checking in advance through regulatory consultancy prevents delays. The permit cannot be used outside its scope or validity period and cannot be transferred to another company.