A small modular reactor (SMR) is a nuclear reactor, usually with an electrical output of 300 MWe or less, whose modules are manufactured in a factory and transported to the site for installation. Its logistics differs from that of a large plant: instead of one-off giant components, there are standard-sized, serial and repeated shipments, and the emphasis of quality control shifts to the factory.
What sets an SMR apart from a large reactor?
A conventional power reactor generates around 1,000 MWe or more per unit; the VVER-1200 units at Akkuyu are in this class. SMRs, by contrast, are generally below 300 MWe. Designs below 20 MWe are called micro reactors. The word "modular" describes not only size but the production method: components, or even the entire reactor module, are manufactured in a factory under controlled conditions, replicated in series and assembled on site. According to the World Nuclear Association, more than 100 SMR designs are under development.
What examples exist worldwide?
| Project | Country | Status |
|---|---|---|
| Akademik Lomonosov (2 × KLT-40S) | Russia, Pevek | Floating plant; in commercial operation since May 2020 |
| Shidaowan HTR-PM | China | Two high-temperature gas-cooled modules; entered commercial operation in December 2023 |
| Linglong One (ACP100, 125 MWe) | China, Hainan | Construction began in 2021; commissioning expected in 2026 |
| Darlington BWRX-300 | Canada | Construction licence April 2025; operation targeted to start in 2030 |
| Ust-Kuyga (2 × RITM-200N) | Russia, Yakutia | Land-based plant; construction licence granted in April 2023 |
Why is the logistics different?
Component size and transport mode
In a large plant, single pieces such as the reactor pressure vessel weigh hundreds of tonnes and can often only reach a site close to a jetty by sea (see why reactor equipment travels by sea). SMR designers, on the other hand, try to keep modules within dimensions that can be moved by road, rail or barge. Even so, in integral designs the steam generator and pressuriser are housed inside the reactor vessel, so the module can be a single but large piece; this is why an out-of-gauge road permit is still needed in most SMR projects.
Serial shipments
The heavy components of a large plant are moved once every few years. The SMR model, by contrast, envisages the same module being sent to different sites again and again. This means the route survey, permit template, transport frame and lashing plan can be developed once and reused. Standard dimensions are the main factor that lowers logistics costs.
The quality point shifts to the factory
Because most welding, assembly and testing is done in the factory, protecting the module during transport to site becomes even more important. Shock and tilt records, humidity control and preservation conditions are the evidence that keeps the factory test results valid.
On-site movement
On site, modules are usually moved with SPMTs and set in place with high-capacity cranes. Compared with the dome or pressure vessel lifts of a large plant, the lifts are lighter but more numerous.
Fuel
Some advanced designs use high-assay low-enriched uranium (HALEU; uranium-235 content between 5 and 20 per cent). The World Nuclear Association notes that new or modified transport packages will be needed to transport this fuel in large quantities.
Large plant vs SMR logistics
| Topic | Large plant | SMR |
|---|---|---|
| Number of heavy components | Few but very heavy | More, in standard sizes |
| Transport mode | Mainly sea plus a short road leg | Road, rail and barge options |
| Planning | Project-specific, one-off | Repeatable template |
| On-site labour | High | Lower |