A dummy fuel assembly is a mock-up that resembles a real fuel assembly in size, weight and hydraulic resistance but contains no uranium and is not radioactive. It is loaded into the reactor core during commissioning, so that the loading rehearsal and primary circuit tests can be carried out without putting real fuel at risk. In June 2026, 163 dummy assemblies were loaded into Akkuyu Unit 1.
What does a dummy fuel assembly look like?
In a pressurised water reactor, fuel is placed in the core in assemblies made up of long, thin rods. A VVER-1200 core consists of 163 fuel assemblies. From the outside, a dummy assembly is identical to the real one: the same top and bottom nozzles, the same grid structure, the same external dimensions. The difference is inside the rods: instead of uranium dioxide pellets, they contain non-radioactive filler or metal rods. Weight and resistance to water flow are kept close to those of a real assembly so that the tests are realistic.
Why is it loaded?
- Full loading rehearsal: The refuelling machine, core map, crews' shift pattern and recording system are tested before the real fuel arrives. Loading all 163 assemblies means testing the procedure from start to finish.
- Cold hydraulic tests: The primary circuit is checked for leak-tightness by raising it to about 1.5 times the operating pressure. At Akkuyu 1, the pressure in these tests reached 24.5 MPa.
- Hot functional tests: The main circulation pumps are started and the circuit is brought close to operating temperature. Because dummy assemblies are in the core, flow distribution and vibration are measured under conditions similar to operation.
- Protecting the fuel: Foreign material left over from installation can be carried along in the first circulations. At this stage, any assembly that gets damaged is a mock-up, not real fuel.
At which stage of commissioning does it take place?
- Installation and cleaning of the primary circuit are completed.
- The dummy assemblies are loaded into the reactor.
- Cold hydraulic tests are carried out.
- Hot functional tests are carried out.
- The reactor is opened, the dummy assemblies are removed and the internal surfaces are inspected.
- With the regulator's permission, real fuel is loaded and physical start-up begins.
At Akkuyu 1, the dummy assemblies were loaded in June 2026; the cold hydraulic tests that began in June were completed at the start of October 2026, and the next step is the hot tests to be carried out at no less than 260 °C. At the Rooppur plant in Bangladesh, dummy assemblies were loaded in September 2024 and the tests were completed in 2025. All stages are explained in the entry on the commissioning process.
How does it differ from real fuel?
| Feature | Dummy assembly | Fresh fuel assembly |
|---|---|---|
| Content | Uranium-free filler or metal | Low-enriched uranium dioxide |
| Radioactivity | None | Low, but contains fissile material |
| Transport rule | General cargo; outside the scope of ADR | ADR/IMDG Class 7, approved package |
| Permits and protection | Commercial shipping documents | State permit and physical protection plan |
| Time in the core | Throughout the tests | Throughout the fuel cycle |
The transport of real fuel is covered separately in the entry on fresh nuclear fuel transport.
How is a dummy assembly transported?
Because it is not radioactive, a dummy assembly does not fall under dangerous goods rules; like most nuclear power plant equipment, it is carried as general cargo. However, as a long, thin structure exceeding 4 metres, it is sensitive to bending and impact. The assemblies are shipped horizontally in special crates that support them along their entire length; shock and tilt indicators are often fitted to the crates. The cleanliness requirement is the same as for real fuel, because the assembly will enter the reactor core. The KKS code, serial number and passport are checked during the delivery inspection on site. On site, the polar crane that lifts the reactor head and the refuelling machine are the main equipment for this operation. The shipment is planned within the framework of nuclear project transport.