Get a Quote
Social Media

What is a dummy fuel assembly and why is it loaded?

Last updated:

Short Answer — Dummy Fuel

A dummy fuel assembly is a mock-up that resembles a real fuel assembly in size, weight and hydraulic resistance but contains no uranium and is not radioactive. It is loaded into the reactor core during commissioning, so that the loading rehearsal and primary circuit tests can be carried out without putting real fuel at risk. In June 2026, 163 dummy assemblies were loaded into Akkuyu Unit 1.

What does a dummy fuel assembly look like?

In a pressurised water reactor, fuel is placed in the core in assemblies made up of long, thin rods. A VVER-1200 core consists of 163 fuel assemblies. From the outside, a dummy assembly is identical to the real one: the same top and bottom nozzles, the same grid structure, the same external dimensions. The difference is inside the rods: instead of uranium dioxide pellets, they contain non-radioactive filler or metal rods. Weight and resistance to water flow are kept close to those of a real assembly so that the tests are realistic.

Why is it loaded?

  • Full loading rehearsal: The refuelling machine, core map, crews' shift pattern and recording system are tested before the real fuel arrives. Loading all 163 assemblies means testing the procedure from start to finish.
  • Cold hydraulic tests: The primary circuit is checked for leak-tightness by raising it to about 1.5 times the operating pressure. At Akkuyu 1, the pressure in these tests reached 24.5 MPa.
  • Hot functional tests: The main circulation pumps are started and the circuit is brought close to operating temperature. Because dummy assemblies are in the core, flow distribution and vibration are measured under conditions similar to operation.
  • Protecting the fuel: Foreign material left over from installation can be carried along in the first circulations. At this stage, any assembly that gets damaged is a mock-up, not real fuel.

At which stage of commissioning does it take place?

  1. Installation and cleaning of the primary circuit are completed.
  2. The dummy assemblies are loaded into the reactor.
  3. Cold hydraulic tests are carried out.
  4. Hot functional tests are carried out.
  5. The reactor is opened, the dummy assemblies are removed and the internal surfaces are inspected.
  6. With the regulator's permission, real fuel is loaded and physical start-up begins.

At Akkuyu 1, the dummy assemblies were loaded in June 2026; the cold hydraulic tests that began in June were completed at the start of October 2026, and the next step is the hot tests to be carried out at no less than 260 °C. At the Rooppur plant in Bangladesh, dummy assemblies were loaded in September 2024 and the tests were completed in 2025. All stages are explained in the entry on the commissioning process.

How does it differ from real fuel?

FeatureDummy assemblyFresh fuel assembly
ContentUranium-free filler or metalLow-enriched uranium dioxide
RadioactivityNoneLow, but contains fissile material
Transport ruleGeneral cargo; outside the scope of ADRADR/IMDG Class 7, approved package
Permits and protectionCommercial shipping documentsState permit and physical protection plan
Time in the coreThroughout the testsThroughout the fuel cycle

The transport of real fuel is covered separately in the entry on fresh nuclear fuel transport.

How is a dummy assembly transported?

Because it is not radioactive, a dummy assembly does not fall under dangerous goods rules; like most nuclear power plant equipment, it is carried as general cargo. However, as a long, thin structure exceeding 4 metres, it is sensitive to bending and impact. The assemblies are shipped horizontally in special crates that support them along their entire length; shock and tilt indicators are often fitted to the crates. The cleanliness requirement is the same as for real fuel, because the assembly will enter the reactor core. The KKS code, serial number and passport are checked during the delivery inspection on site. On site, the polar crane that lifts the reactor head and the refuelling machine are the main equipment for this operation. The shipment is planned within the framework of nuclear project transport.

Frequently Asked Questions

Does a dummy fuel assembly become radioactive after the tests?
Because there is no uranium in the core, no chain reaction and no associated neutron flux occur. Therefore no significant activation is expected in dummy assemblies. The assemblies removed after testing are nevertheless inspected for foreign material and wear; the findings provide information on the cleanliness of the primary circuit, and a decision is made on whether additional cleaning is needed before real fuel is loaded.
Why is the entire core filled with dummy assemblies?
If part of the core were left empty, coolant would pass easily through the empty channels and the flow distribution would not reflect real operation. Filling all 163 positions in a VVER-1200 makes the hydraulic conditions realistic and allows the loading procedure to be tested for every position. The same core map and the same sequence are followed during the real loading.

Published: 17.11.2026 · Voltim Global