Why are bridge and culvert checks carried out in heavy haul transport?

Last updated:

Short Answer — Bridge and Culvert Checks

In heavy haul transport, bridge and culvert checks are carried out to determine in advance whether the structures along the route can safely carry the abnormal load. Bridges are designed for standard traffic loads, and a combination weighing hundreds of tonnes can exceed these values. The checks prevent permanent damage, culvert collapse and the transport coming to a halt on the road.

Why is a bridge assessed separately?

A bridge is designed using the standard vehicle loads and safety factors in the design code. An abnormal load combination departs from this model in three ways: its total weight is very high, the weight is concentrated over a short length, and the vehicle crosses the most heavily stressed part of the bridge on its own. The girders, deck, bearings and piers must be able to carry this effect. How total weight and axle loads are distributed is explained in the axle load calculation entry.

The decisive variables are:

  • Total weight and combination length: When the same weight is spread over a longer vehicle, the bending effect on the span decreases.
  • Axle spacing and axle line load: These determine local stress on short-span bridges and on the deck.
  • Age and condition of the bridge: Corrosion, cracks or bearing damage reduce capacity.
  • Dynamic effect: Vibration and impact increase with speed; this is why crossings are usually made at very low speed.

Why are culverts risky?

A culvert is a pipe, box or arch structure that carries water under a road embankment, and it is often invisible to the driver. If the fill above it is thin, the wheel load reaches the structure directly. Old concrete pipes can be crushed, the roof of a box culvert can crack and the approach fill can settle. The damage is not always noticed immediately; the road collapses at the first rainfall. This is why the location, type and fill depth of each culvert on a heavy haul route are recorded one by one.

Who approves?

Article 128 of the Highway Traffic Regulation (Karayolları Trafik Yönetmeliği) requires the General Directorate of Highways (Karayolları Genel Müdürlüğü, KGM) to take the condition of roads and bridges into account when granting an abnormal load permit. Under the KGM Regulation on Duties, Powers and Responsibilities, the Department of Structures (Sanat Yapıları Dairesi Başkanlığı) gives its opinion, from the point of view of engineering structures, on the transport of indivisible loads whose weight or dimensions exceed the legal limits. On municipal roads the approval of the relevant municipality, and on motorways that of the operator, may also be required. Structural calculations are usually prepared by a civil engineer appointed by the carrier or the cargo owner; the decision rests with the administration.

How is the check carried out?

  1. Inventory: During the route survey, all bridges and culverts are listed with their spans and visible condition.
  2. Pre-screening: The load model of the combination is compared with the known capacity of the bridge; critical structures are identified.
  3. Structural assessment: Calculations based on design drawings or as-built surveys are made for critical structures.
  4. Crossing conditions: Speed limit, single-vehicle crossing along the centre of the carriageway, no stopping on the bridge, closure to traffic.
  5. Monitoring during the crossing: Some projects use deflection measurement or observers; the structure is inspected again afterwards.

These steps are written into the transport's method statement.

What if a bridge is inadequate?

MethodWhen is it suitable?
Alternative routeIf a reasonable detour exists; often the cheapest solution
Adding axle linesWith modular hydraulic trailers, the load is spread over a longer area
Temporary bridge or over-bridge platformTo carry the load over short-span, weak structures
Temporary support (strengthening)If a tower or shoring can be erected at mid-span
Temporary road through the stream bedIn the dry season, at small streams
Reducing cargo weightIf removable parts or liquid contents can be shipped separately

Common mistakes

  • Listing only bridges and skipping culverts.
  • Using catalogue values instead of the combination's actual axle spacings.
  • Not coordinating the crossing conditions with the traffic police escort; police support may be needed to stop traffic on the bridge.

Frequently Asked Questions

Why does the vehicle move so slowly when crossing a bridge?
As speed increases, the dynamic interaction between the vehicle and the bridge grows and the effect on the structure rises above the static load. Very low speed keeps this additional effect small and also makes it easier for the vehicle to travel along the centre of the lane, balanced on the bridge axis. The speed limit is set in writing in the permit or the method statement.
Above what weight is a bridge check required?
There is no fixed tonnage threshold; the decision depends on the total weight of the combination, the axle loads and the condition of the structures on the route. No additional assessment is made for a vehicle within legal limits. For heavy loads exceeding the limits, KGM takes engineering structures into account in its permit assessment and requests additional information or calculations where necessary; in heavy load planning, this time is added to the schedule.
Can bridge crossings be avoided entirely by using sea transport?
Sometimes. For facilities near the coast, equipment can be brought directly to a jetty or temporary ramp, reducing the road distance to a few kilometres. This approach reduces both the number of bridges and the permit time; details are in the shipping out-of-gauge cargo by sea entry. The port, jetty and short site road must still be checked for load-bearing capacity.